M/Y World Is Not Enough

Project Overview

Yacht Engineering carried out the retrofit and integration of an ASEA shore power converter system onboard M/Y World Is Not Enough.

The project included engineering and installation works required to integrate the shore power conversion equipment with the yacht's existing electrical distribution system.

The retrofit was performed to provide reliable shore-side electrical supply compatibility and improve the yacht's operational flexibility when connecting to different marina and shore power networks.

Scope of Work

  • Technical assessment of the existing shore power system
  • Retrofit engineering and installation planning
  • Installation of ASEA shore power converter equipment
  • Electrical integration with the yacht's existing power distribution system
  • Connection and modification of associated electrical circuits
  • System configuration and setup
  • Functional testing
  • Commissioning of the completed system

Shore Power Retrofit

Shore power conversion systems allow a yacht to accept electrical supply from shore networks with different voltage and frequency characteristics while maintaining a stable onboard electrical supply.

Integration of this type of equipment requires careful coordination with the vessel's switchboards, protection systems, cabling and existing electrical infrastructure.